RFI from Accurange3000 distomat

Links:
20apr11:rfi on telescope using 327 rcvr accurange3000 distomat.
06apr11:rfi from accurange3000 distomat in screen room.

Accurnage3000 distomat hardware page


20apr11: rfi on telescope using 327 rcvr. (top)

    The rfi from the Accurange3000 distomat was tested on 20apr11. The setup was:

327 test:

    The power on,off sequence was:

The dynamic spectra show the on,off sequence (dashed horizontal lines):

lbw test:

    The power on,off sequence for lbw was:
The dynamic spectra show the on,off sequence (dashed horizontal lines):

Summary

processing: x101/110420/chkdistnew.pro

06apr11: rfi from accurange3000 distomat in screen room.

    The accurange 3000 distomat was  being tested to replace the laser rangers. On 06apr11 an accurange 3000 laser was tested by luis quintero in the screened room using a probe and  spectrum analyzer. The setup was:
The plots show the results of the measurements (.ps) (.pdf):

Summary:

processing: x101/110406/dolaser.pro