Pointing errors after platform reinforcement

10feb11




    The telescope beam reinforcement finished on 05feb11. The time line was:
This work added weight to the platform. The final distribution of  new weight should be symmetric so the pointing should not be affected (other than the platform will now be lower at a fixed tiedown position).

   

After the work, pointing runs were done on:
The plots show the results of the pointing runs (.ps) (.pdf):
the results are summarized in the table below:

data set
offsets (asecs)
rms err (asecs)

za
az
za
az
07-09feb11
-4.40
3.17
3.76
6.89
dec10-jan11
-5.06
0.35
5.23
6.11
All Data
-4.78
1.55
4.67
6.60





All Data (except B0428+205)
-4.60 0.73
4.79
5.87
All Data lbw
-5.25
1.85
4.51
6.19
All Data cband
-3.67
0.85
4.85
7.42



Summary:

processing: x101/110204/x102..pro